STAGE 3 - BUILDING REGULATIONS |
|
Upon receipt of planning approval, it will then be necessary to add further technical /construction information and submit a BUILDING REGULATION application. Approval is granted in about 2-3 weeks from submission and again may be approved subject to conditions requiring further detail information to be submitted (typically minor details of technical specification.)
It may also become necessary to include items of Structure Engineering detail and we can assist in this by obtaining quotations on your behalf.
Together with the approved planning drawings and detailed working drawings for Building Regulation approval, an accurate cost of the works and full specification of fixtures and fittings can be agreed between the client and their preferred builder.
Building works can commence when full planning and building regulation approvals have been obtained and it is usual for your building contractor to notify both the planning and building control sections of your local authority at least 1 week before site works commencing.
|